I’ts official: the cost estimates of Landsvirkjun, the National Power Company, for Karahnjukar were false and the numerous economists and even the National Planning Agency, who criticized Landsvirkjun for massaging their economic data were dead right. The new cost estimate for Kárahnjúkar was presented by Minister of Industry Össur Skarphedinsson at the Althingi parliament yesterday.
According to Skarphedinsson the total cost of constructing the dams and the hydropower plant at Fljotsdalur has exceeded estimates by ISK 17.7 billion (USD 264 million, EUR 172 million) and is now expected to amount to ISK 133.3 billion (USD 2.0 billion, EUR 1.3 billion). MP for the Left-Greens Álfheidur Ingadóttir said until yesterday people had not been aware of by how much cost estimates were exceeded. Ingadóttir criticized the minister for not taking the cost of agreements with contractors into account. She argued that by including such agreements the original cost estimate is exceeded by an even higher amount, ISK 32.5 billion (USD 484 million, EUR 315 million).