No Joint Assessment Needed in Reykjanes


Power LinesIn September 2009, the Ministry of Environment overruled the Planning Agency’s verdic which stated that no joint Environmental Impact Assessment (EIA) is needed for the S-West Power Grid and the industry that it’s going to be providing for. The case was sent back to the Planning Agency for a more substansial treatment.

This ruling caused uproar amongst pro-indistrialists, who went so far as to claiming that Svandís Svavarsdóttir, the minister of environment, was guilty of both treason and terrorism against the people og Reykjanes, especially all the unemployed. All the medias jumped on the wagon with the industrialists, citing union bosses worrying about the unemployment rate, economists painting a bleak picture of a bankrupt future and interviews with unemplyed people worrying about their mortages. And all of it was Svandís’s fault.

Yesterday the Ministry of Environment confirmed the Planning Agency’s second verdict. The verdict’s the same, no joint EIA is needed for the projects on the SW peninsular. This means that all the balls are in the industrialists court now and the media is backing them up with quotes and interviews with indistrial workers and union bosses dreaming of a better future now that the way has been paved for projects like the enlargement of the Reykjanes Power Plant, Bitra Power Plant, Hverahlíða Power Plant, various data storages and an aluminium smelter and a silicon factory in Helguvík.

Read More

Oct 10 2009
1 Comment

Blame Canada? – Geothermal Energy, Swedish Shelf Companies and the Privatisation of Iceland


From The Reykjavík Grapevine, by Catharine Fulton – One by one men in suits of varying shades of grey approached the podium in the pit of the Reykjavík City Hall. One by one they pleaded their cases while Reykjavík’s esteemed mayor—the fourth in two years—Ms. Hanna Birna Kristjánsdóttir looked on appearing disinterested in what appeared to be solely a formality. As the council members continued selling the idea of selling Iceland’s resources, a crowd of 100-strong grew more agitated and increasingly vocal from their perch in the viewing gallery of the hall, separated from having a say in their own natural resources by an aesthetically pleasing glass barrier.

“People were screaming, saying that the politicians were traitors,” explained Jón Bjarki Magnússon, a student who arrived at City Hall just in time for the vote. “It was a weird feeling to see it happen, to see these people down on the floor raise their hands and the decision is made and to see all these angry people above them not able to do anything.”

The September 15th city council meeting stretched on for over three hours, during which time onlookers shouted and boo-ed as city council progressed toward approving the 32.32% sale of Iceland’s HS Orka to the Canadian-cum-Swedish firm Magma Energy Corp. Read More

Mar 03 2009

Draft of Law about Helguvík Approved


Iceland’s current government, formed by the Left-Green Party (Vinstri Grænir) and the Social Democratic Alliance (Samfylkingin), has approved draft of a law by Össur Skarphéðinsson, minister of industry. The draft permits the government’s contract with Century Aluminum and Norðurál Helguvík about the construction of an aluminium smelter in Helguvík.

The contract includes several versions of a “special treatment” that Norðurál will get from the government and has e.g. to do with the amount of taxes that the company will pay. The contract puts Norðurál in a different and higher position that other companies in Iceland, apart from Alcoa’s aluminium smelter in Reyðarfjörður and Century’s smelter in Grundartangi. Read More

Feb 03 2009

Þjórsárver Wetlands to be Protected but Construction of Helguvík Smelter Continues


Iceland’s new minister of environment and a Left Green MP, Kolbrún Halldórsdóttir has announced that one of here first jobs in the government will be to protect the Þjórsárver wetlands. At the same time she has said that Norðurál’s (Century Aluminum) plans for a new aluminium smelter in Helguvík, can most likely not be stopped by any future government. While in opposition, the Left Greens always spoke against the construction in Helguvík.

Þjórsárver are a unique ecosystem characterized by tundra meadows intersected with numerous glacial and spring-fed streams, a large number of pools, ponds, lakes and marshes, and rare permafrost mounds. Iceland’s national energy company, Landsvirkjun wanted to build a 30 meters high dam in the area, creating a 65 km2 big reservoir. The energy was supposed to run the enlargement of Rio Tinto Alcan’s aluminium smelter in Hafnarfjörður, a plan that the majority of the town’s population voted against in a local referendum in 2007. Later Landsvirkjun proposed to lower the planned dam down to 24 meters. Halldórsdóttir’s decision about the protection of Þjórsárver is very important and a big victory for the Icelandic environmental movement.

Iceland’s new minority government, formed by Samfylkingin (the Social Democratic Alliance) and Vinstri Grænir (VG – The Left Greens), has released it’s policy statement for the upcoming 80 days until parliamentary elections will take place in the end of April. The statement states e.g. that “no new plans for aluminium smelters are on the government’s list.” Still Össur Skarphéðinsson, a Samfylkingin MP and the minister of industry since 2007, has said that both Norðurál’s planned 360 thousand ton smelter in Helguvík and Alcoa’s planned smelter in Bakki, Húsavík, do not fall under this statement. Read More

Jan 13 2009

Eight Power Plants Needed for Helguvík Smelter


The directors of Reykjavík Energy (OR) and Hitaveita Suðurnesja (HS) have both said that the companies are not able to supply all the necessary energy that Century Aluminium needs fo it’s planned aluminium smelter in Helguvík, in the next 7 years, even though 6 new power plants would be built. At least 200 MW would be needed, which is the amount of energy that could be produced by building power plants in Bitra (geothermal field) and in Urriðafoss waterfall (in Þjórsá river).

Össur Skarphéðinsson, minister of industry has on behalf of the Icelandic government, given Norðurál (Century Aluminium) the permission to build up to 360 thousand ton aluminium smelter in Helguvík, which would produce double the amount Rio Tinto Alcan’s smelter in Hafnarfjörður produces. But where does all the necessary energy – 625 MW – come from?

Read More

Mar 30 2007

Countdown to the Hafnarfjordur Referendum…


Iceland’s path as either a wild green masterpiece or a mid-Atlantic industrially polluted backwater is to reach a significant junction tomorow, Saturday the 31st of March. Residents of Hafnarfjordur, SW of Reykjavik, will vote on whether they want their Alcan (Canadian Aluminium) smelter expanded into by far the biggest aluminium smelter seen in Iceland to date.

The smelter, which lies in the vicinity of Hafnarfjordur, in Straumsvik, currently has a capacity of being able to produce 180,000 metric tonnes of aluminium per year (mtpy.) Alcan wishes to turn this into an unbelievably massive 460,000 mtpy smelter.

Iceland’s current largest smelter asside from this, being built in Reydarfjordur, can produce a gigantic 322,000 mtpy of aluminium and is to be powered by damming the Central-Eastern of Icelands: the infamous Karahnjukar project.

If the smelter in Hafnarfjordur is to be enlarged then we will be facing the destruction of Iceland’s Central Southern Highlands – Langisjor, Kerlingarfjoll, Thjorsarver, the nether region of Thjorsa not to mention the geothermal fields in Reykjanes and so much more.

To anyone who has the opportunity to vote in this referendum, please vote to keep Iceland a wild and green masterpiece.